A Chara,
Please accept this submission in respect to the above-referenced planning application. Uisce Éireann (UÉ) has reviewed the plans and particulars submitted with the application and have the following observation(s).
Uisce Éireann’s Recommendation: No Objection in Principle
Uisce Éireann’s Assessment/Observation(s): The applicant has engaged with Uisce Éireann via a Pre-Connection Enquiry and Uisce Éireann can confirm that a Confirmation of Feasibility CDS23001316 has been issued to the applicant advising that water and wastewater connections are feasible. The wastewater connection is feasible subject to upgrades. There are 3 potential options available for this wastewater connection which are detailed in the Confirmation of Feasibility. A detailed assessment of the applicant’s proposed wastewater connection point will be undertaken at connection application stage.
Uisce Éireann’s Standard Condition(s):
1. The applicant shall enter into a Connection Agreement(s) with Uisce Éireann to provide for a service connection(s) to the public water supply and/or wastewater collection network and adhere to the standards and conditions set out in that agreement.
2. All development shall be carried out in compliance with Uisce Éireann’s Standard Details and Codes of Practice. Reason: To provide adequate water and wastewater facilities. Queries relating to the terms and observations above should be directed to planning@water.ie
PP Ali Robinson
Signed on behalf of Dermot Phelan Connections and Developer Services